NGCP AND CENECO SET POWER INTERRUPTION ON DECEMBER 9

Header

Bacolod City
Dec. 09 - 08:00 AM to 05:00 PM
Community

The National Grid Corporation of the Philippines is scheduling a power service interruption to Central Negros Electric Cooperative, Inc. Sum-ag and Lag-asan substations on December 9, Sunday.

CENECO shall take advantage of this downtime by implementing simultaneous maintenance activities. This is to ensure stability of distribution lines and avoid further serious damages that will result to major interruptions. Details of these outages are as follow:

Date: December 9, 2018 - Sunday
Reasons: 
• NGCP will conduct replacement of poles, cross-arm and insulators at structure numbers 17, 18, 19, 70, 72, 83, 128, 131, 237, 286 and 313;
• Preventive Maintenance Servicing of 10MVA Power Transformer of Sum-ag substation at Crossing Sum-ag – Abuanan Road, Brgy. Sum-ag, Bacolod City, 10MVA Power Transformer of Hilangban substation at Hacienda Hilangban, Brgy. Lag-asan, Bago City;
• Replacement of rotten poles covering Sum-ag Feeders 1 and 2; and
• Tree trimming covering Sum-ag Feeders 1 and 2, and Hilangban Feeders 1, 2, 3 and 4.

Time: 8:00AM to 5:00PM 
Areas Affected: Bacolod-San Enrique 69kV Transmission Line

SF1 From Sum-ag Substation to Sum-ag Highway, whole of Pta. Taytay Road including VMA, Sum–ag Highway to Medalla Elementary School near CEGASCO, Brgy. Pahanocoy, Pahanocoy Village (NHA Housing), Brgy. Road from BanggaTomaro to Brgy. Cabug and along Circumferential Road from Araneta down to HJR Prawn Processing, Boundary of Bago City and Bacolod City including Fiesta Homes Subd., Prk. KBS and San Sebastian Village up to Pta. Taytay Elementary School, Brgy. Firmville executive, Villa Maria Reyna South, BanggaTotong, Had. Edmar, Handumanan, Brgy. Felisa, Prk. Maasin&Prk. Sta. Rita, Dulao, Prk. Tumpok&Prk. Overflow, Blumentritt.

SF2 From Sum-ag Substation along Abuanan Road (Sum-ag) to portion of Bago, Brgy. Tabunan, Brgy. Dulao, Brgy. Atipuluhanand Brgy. Abuanan, Sayson Piggery, Quiet Place Resort, GC&C Crusher, Prk. Sambag, Prk. Cadena de Amor, Prk. Rose 1 & 2.

HF1 Portion of Brgy Lag-asan, Brgy. Balingasag, Bago City College, Prk. Kapahuan 1 & 2, Bago City Hospital, Prk. Santan, San Esteban Phase 2, Sta. Catalina Subdivision, Brgy. Sampinit, CF1, CF2, San Gabriel Subd., Villa Cristita, Carmella Homes, Prk. Camingawan, Prk. San Francisco, BrgyCalumanggan, Prk. Flower, Prk. Paraiso, Brgy. Taloc, Prk, Newton, Cawayanan.

HF2 The wholearea of Bago City including San Esteban Phase 1, Brgy. Poblacion, Pta. Playa, Prk. Batad, Prk. Malipayon, Baywalk.

HF3 Crossing Ubay,Bago Eco-Center,Humberto’s Resort, Hda. Pili, Brgy. Pacol, Brgy. Bagroy, Brgy. Sagasa, Brgy. Caridad, Brgy. Allanza, Brgy. Don Jorge Araneta (Central Ma-ao)

HF4 Lag-asan relocation site, Brgy. Napoles, Brgy. Malingin, Crossing Mining, Brgy. Ma-ao, Villa Cresteta, Brgy. Bacong, Brgy. Binobuhan, Brgy. Mailum, Brgy. Ilijan, Viva Mineral Water, Buenos Aires Resort, Brgy. Manghumay, PNOC-EDC

Electricity consumers are further advised that, in the event of any power interruption, electrical switch/es should be turned-off for safety reasons. When electricity supply resumes, please provide allowance of about 10-15 minutes before switching on all electrical appliances and facilities to avoid power surge. For inquiries, please call your CENECO Call Center at telephone numbers 709-1256, 709-1257, and 458-6777 local 1101, 1102, 1103 and 1107. 
Sorry for the inconvenience.